StockMarketWire.com - Serinus Energy said key machinery for its Moftinu gas plant in Romania had been loaded onto a freighter and were currently bound for Germany.

The two pieces of kit in transit included a low-temperature separation unit and a triethylene glycol unit.

They had been loaded onto a freighter in Halifax, Canada and were expected to arrive at the port of Bremerhaven around six-to-10 days after departure.

The units would them be trucked to the Moftinu site in Romania for final assembly, testing and commissioning.

Serinus said it would inform the market of the production start-up date once the delivery, installation and commissioning of the units had been achieved.


At 8:24am: [LON:SENX] Serinus Energy Plc Ord Npv share price was +0.25p at 15.25p



Story provided by StockMarketWire.com