StockMarketWire.com - Trans-Siberian Gold reports that mine development at Asacha in Q2 comprised 686 metres. Development metres were lower in June due to excessive, and abnormal, water flow, however this is not expected to have any impact on future production.

Ore extraction (including ore from stoping and mine development) amounted to 44,535 mt. In the first half of 2015, an average 13,252 mt per month was processed through the Asacha plant.

The average gold grade in ore delivered to the plant in the first half of 2015 was 13.5% higher than in the corresponding period of 2014. Year to date production of gold in dore and refined gold was, respectively, 15.5% and 8.5% higher than in the first half of 2014.