StockMarketWire.com - TomCo Energy said the commencement of field test at its Holliday A Block in Utah had been pushed back by two-to-three weeks.

The pause had been caused by a a slight delay to the arrival of bespoke ceramic parts required for the field.

As a result, the drilling of the three new wells for the field test has now been scheduled for mid July.

Otherwise, TomCo said a substantial proportion of preparatory work for a field test at its Holliday A Block in Utah had been completed.

The company said that following a recent site visit, it had, together with Himes Drilling Company and IGES determined the location of the three new wells for the field test.

Road improvement works and pad construction had been completed at the new site.

An exploration permit variation application had meanwhile been submitted, with approval expected shortly.




Story provided by StockMarketWire.com