StockMarketWire.com - W Resources said that commissioning of the jig and mill plant had commenced at the La Parrilla mine in Spain.

The facilities would upgrade the La Parrilla ore, efficiently reject barren material and prepare material for feed to the concentrator plant.

W said it would feed 100% of the output of the jig and mill plant once fully commissioned to the existing concentrator plant with upgraded and milled mine feed allowing a 'significant upgrade' in production rates.

At the concentrator plant, 90% of all structural steel and primary equipment was now on-site and being installed, ahead of its scheduled completion this quarter.