StockMarketWire.com - Sunrise Resources said there had been a delay to the completion of mine permitting for its CS pozzolan-perlite project in Nevada.

The company said the delay had been caused by the late introduction by the US Bureau of Land Management of some additional reporting requirements for a supplemental environmental report.

Completion of the permit was expected to be pushed into early 2020, it added.